PPC : Review of the PPC Charging Scheme : Meetings : 18th June
2008
PPC Stakeholder Group Meeting
Wednesday 18th June 2008 @ SEPA Boardroom, Riccarton
Office
| |
Discussion |
Actions |
| 1 |
Present: R Robertson (S.Govt), S Bygrave
(UKPIA), P Loggie (NFUS), M Garden (SWA), I Norton (SWA), D Morgan
(CPI), K Morrison (SP) , S Freeman (CPL), S Freeland (SESA), C
Bayes (SEPA) J Shaw (SEPA), J Burns (SEPA), I Halliday (SEPA), F
Weir (SEPA), N Donnelly (SEPA)
|
|
| 2 |
Apologies: D Forest (UKPIA) P Smith (N
Grid), P Monger (PRA), A Willox (FSB), B Martin (Scot Eng), J
Sheridan (QPA), I Stewart (CIA) |
|
| 3 |
C Bayes: Welcome.
The Chair noted with thanks the time, effort and support that Derek
Forest had afforded the PPC Stakeholder Group & wished him well
in his forthcoming retirement.
|
|
| 4 |
Previous Minutes: Approved
|
|
| 5 |
Matters Arising: Revision of Part A template
will be concluded when staff are available. JWB to advise on
proposed time scale.
|
JWB |
| 6 |
Odour Guidance Introduction – presentation by
Fiona Weir (SEPA)
The proposed guidance has been introduced to consolidate the
existing guidance which is currently spread over a variety of
documents and to provide a format where subjective decisions
relating to odour can be taken through compliance with a formalised
methodology.
This Guidance will undergo a 12 week consultation which will
conclude on 29th August, trade federations were encouraged to
provide comment.
Consultation Documents are available at :-Closed Consultation
|
ALL |
| 7 |
Compliance Scheme Update – presentation by John
W Burns (SEPA)
The stakeholder workshop day held on 7th May was extremely well
attended with many trade associations represented.
Scheme will cover all regulatory schemes other than COMAH and some
areas within CAR.
Pilot scheme will be run with volunteer sites – sites wishing to
volunteer should submit their names to Norman Donnelly (SEPA)
The proposed trails will support the project plan which has a
publication Date of Dec 2008 with implementation scheduled for Jan
2009. PPC Pt A and PPC Pt B sites will move onto the scheme during
2009 with indicative costs being provided for each site for 2010 as
information only. Provided agreement on the effectiveness of the
scheme is supported then full implementation of new costs will
occur in 2011.
|
TA's |
| 8 |
Charging Scheme Review – presentation by John W
Burns (SEPA)
Overview of development of charging scheme including a review of
Phase 1 which is now complete and an introduction to Phase 2.
Variants of the financial model were introduced to display cost
reclamation options.
Current intention is to use 2010 as a baseline year to model
changes that will be developed through Phase 2.
|
All |
| 9 |
IPPC Directive Review – presentation by Ian
Halliday (SEPA)
Proposed timescale confirmed as follows; Jan 2009 first reading of
directive. Dec 2010 completion of the co-decision process. July
2012 Directive fully transposed into force by member states. The
Directive applies to all new installations from this date onward.
January 2014 – Transfer of existing sectors, previously subject to
IPPC, WID, SED and TiO2 Directive. July 2015 existing installations
performing the newly prescribed activities must meet the
requirements of the new Directive. January 2016 – Large Combustion
Plants must meet the requirements set out in Chapter 2, as well as
the ELVs set out in Annex V.
There was discussion over the current DEFRA consultation (which
closes in July). There were a number of concerns raised over
different issues e.g. reduced thresholds for intensive agriculture,
potentially more prescriptive levels of inspection and the
mandatory nature of Brefs. Trade Associations encouraged to raise
in response to the consultation.
|
TA's |
| 10 |
AOB: None raised.
|
|
| 11 |
DONM:– Fri 10TH October
RICCARTON Board Room in Edinburgh - 10:00 for 10:30.
|