National Waste Strategy

Ayrshire, Dumfries and Galloway
Area Waste Plan

SEPA :: Home Page
spacer
Contents Page Contents Page
Previous Page Previous Page
Next Page Next Page
spacer
spacer   spacer
 

3.4 Indicative Performance Targets for BPEO

Despite the target dates or diversion of MSW from landfill being staged from 2010 to 2020, the overall scale of the task ahead should not be underestimated. By 2020, it is hoped that we can move from current reliance on 96% landfill disposal, to just 28% of total MSW arisings in the area. In tonnage terms this represents almost 360,000 tonnes of biodegradable waste being diverted from landfill across the waste strategy area by 2020 (as modelled at maximum growth rate of 2% each year). This should be compared with the diversion compliance figure of some 240,000 tonnes identified in the Summary of Waste-management tables below).

Figures 3.5, 3.6 and 3.7 and Tables 3.3, 3.4 and 3.5 outline the objectives of the BPEO with respect to waste diversion by the target years 2010, 2013 and 2020. The proportion of waste diverted to each treatment method is also outlined, as are the diversion targets for each target year. It is implicit that all Landfill Directive Targets will be met within the overall BPEO Targets set out throughout this section and contributes to the 25% recycling and composting national target by 2006.

Note the following tables and diagrams share the same underlying assumption. Specifically they are:

Modelled on maximum 2% growth rate 'worst case scenario'–SWMBA (2001) Appendix 2. At 0% plus population change, the tonnages would be almost half.

Model adjusted to avoid double counting of treatment outputs, i.e. water vapour losses are attributed to compost outputs as well as refuse-derived fuel.

Energy from waste refers to pyrolysis/gasification plant in DGC only. The material going to energy recovery is a refuse-derived fuel.

All tonnages are indicative and apply across the WSA. They are intended as a guide rather than rigid targets. Individual local authorities may have a different mix of treatments to achieve the overall diversions and these will be set out in local delivery Implementation Plans.

If required, other appropriate waste recovery technologies will be used after 2010 to enable the 2013 and 2020 diversion targets to be successfully met. These technologies include processes such as thermal treatment and other emerging waste treatment technologies. These technologies will be assessed for suitability by the WSAG and decision taken by 2006.

It should be noted that should recycling and composting activities surpass the percentage shown, then the need for additional technologies will be decreased accordingly. However, should monitoring of the plan indicate that recycling and composting rates will not be sufficient to meet diversion targets, then other appropriate waste-recovery technologies will have to be used to meet the shortfall.

The energy from waste element is based on the 30,000 tonnes of refuse-derived fuel that Dumfries and Galloway will be diverting as specified in the Waste Management/Recycling PFI Project. No additional energy from waste elements have been planned for.


Table 3.3 - Summary of Waste Management by 2010

Objective by 2010
Projected MSW Arisings - 417,000 tonnes per annum
(max 2% growth per annum from SWMBA 2001)
 
Waste Treatment Methods
Composting output: Increased from 3% (1998) to 14%
Recycling output: Increased from 4% (1998) to 19%
Other recovery/treatments: Increased from 0% (1998) to 51%
Landfill: Decreased from 93% (1998) to 59%
Note: Landfill and other recovery treatment processes expressed as input percentage of total MSW. Waste going to other recovery/treatment processes yield composting and recycling outputs hence figure will not add to 100%
 
EC diversion targets
BMW Permitted to landfill = 140,000 tonnes
BMW landfilled using BPEO = 74,000 tonnes
Estimate Diversion Achieved = 187,000 tonnes (of the total tonnes MSW diverted)


Figure 3.5 Schematic of Waste-management Option for MSW by 2010

Figure 3.5 Schematic of Waste-management Option for MSW by 2010


Table 3.4 - Summary of Waste Management by 2013

Objective by 2013
Projected MSW Arisings - 443,000 tonnes per annum
(max 2% growth per annum from SWMBA)
 
Waste Treatment Methods
Composting: Increased from 14% (2010 ) to 16%
Recycling: Increased from 19% (2010) to 23%
Other recovery/treatments: Decreased from 51% (2010) to 49%
Landfill: Decreased from 59% (2010) to 46%
Note: Landfill and other recovery treatment processes expressed as input percentage of total MSW. Waste going to other recovery/treatment processes yield composting and recycling outputs hence figure will not add to 100%
 
EC diversion targets
BMW Permitted to landfill = 93,000 tonnes
BMW landfilled using BPEO = 62,000 tonnes
Estimate Diversion Achieved = 240,000 tonnes (of the total tonnes MSW diverted)


Figure 3.6 - Schematic of Waste-management Option for MSW by 2013

Figure 3.6 - Schematic of Waste-management Option for MSW by 2013


Table 3.5 - Summary of Waste Management by 2020

Objective by 2020
Projected MSW Arisings - 508,000 tonnes per annum
(max 2% growth per annum from SWMBA)
 
Waste Treatment Methods
Composting: Increased from 16% (2013) to 18%
Recycling: Increased from 23% (2013) to 34%
Other recovery/treatment: Decreased from 49% (2013) to 44%
Landfill: Decreased from 46% (2013) to 28%
Note: Landfill and other recovery treatment processes expressed as input percentage of total MSW. Waste going to other recovery/treatment processes yield composting and recycling outputs hence figure will not add to 100%
 
EC diversion targets
BMW Permitted to landfill = 65,000 tonnes
BMW landfilled using BPEO = 43,000 tonnes
Estimate Diversion Achieved = 254,000 tonnes (of the total tonnes MSW diverted)


Figure 3.7 Schematic of Waste-management Option for MSW by 2020

Figure 3.7 Schematic of Waste-management Option for MSW by 2020


The waste strategy group is confident that even under worst-case conditions the EC landfill directive targets will be met. They have already demonstrated a commitment to diverting 72% of their waste away from landfill (see Exec. Summ. Table 2). The key target is the amount of BMW they are allowed to landfill. What the waste strategy group achieve is very much dependent upon the recovery rates of the processes implemented and the participation rates. The BPEO schematics (above) are modelled on recovering 50% of the available recyclate. The schematics use a national set of parameters for the composition of household waste. These parameters are reproduced in Figure 3.8 (below)


Figure 3.8 - Composition of Household Waste

Figure 3.8 - Composition of Household Waste

Source: Department of Environment, 1992-1993 Household Waste Analysis Programme

If we examine the performance of the BPEO against the permitted BMW landfill targets, we can see why the waste strategy group is so confident. Table 3.6 demonstrates that achieving a BMW diversion to satisfy the modelled 'worst-case scenario' is achievable. What is remarkable about this is that no attempt has been made to utilise weight loss from mixed-waste-treatment technologies driving off water vapour and carbon dioxide in the calculations. All the local authorities are looking to introduce some form of additional treatment technology. Dependant on the technology adopted, then between a quarter and half of the weight of waste processed can be diverted as water vapour and CO2, plus they will boost their recycling/composting outputs, plus they can produce an end product suitable for some other use, i.e. not landfilled.

Given that the BPEO seeks additional treatment for approximately half of the waste, then a comfortable margin for error can be counted on. Such an approach also allows the treatment of all the putrescibles plus the 'contaminated' fractions that can't be directly recycled/composted.


Table 3.6 - BMW Diversion Performance

By EC Target Years Waste Strategy Group Performance for Diverting BMW from Landfill BMW Diversion
Composting (garden waste, textiles and wood) Recycling (Paper, card, fuel–DGC only) Energy Recovery (Refuse-derived) Modelled by SWMBA Achieved by BPEO
2010 58,000 40,000 30,000 110,000 128,000
2013 99,000 50,000 30,000 172,000 179,000
2020 156,000 87,000 30,000 240,000 273,000

Source of waste data: SWMBA appendix 2.

The amount of BMW going to Landfill is shown in Table 3.7. These figures can then be compared to the maximum amount of BMW allowed to landfill under the directive, as set out in Table 3.8.


Table 3.7 - BMW Diversion and Landfilling Projections using BPEO

By Year 2010 2013 2020
Total MSW 417,000 443,000 509,000
Total BMW 250,000 266,000 305,000
BMW Diversion achieved by BPEO 128,000 179,000 273,000
BMW Landfilled 122,000 86,000 32,000

Source: Data from SWMBA 2001 Appendix 2 (rounded to nearest thousand)
Calculated from SWMBA (2001) data and LA performance table 2.

The bottom line is that the BPEO is based on a worst-case scenario. It confidently predicts the delivery of the diversion targets (see Table 3.7 above) with a comfortable factor of safety.


Table 3.8 - Delivery of BMW Landfill Targets

By Target Years BMW Permitted to Landfill* BMW Landfilled
(in accordance with the BPEO)
2010 140,000 122,000
2013 93,000 86,000
2020 65,000 32,00

Source: SWMBA 2001 Appendix 2 (rounded to nearest thousand).

Proof of the effectiveness of the BPEO will lie in what it delivers. While the WSAG is reluctant to impose fixed targets without a national framework to follow, it has acknowledged that monitoring and review is required, giving an indication of progress. This principle of monitoring and continuous improvement is central to good management. To ensure that the BPEO objectives will be achieved, the WSAG will need to periodically review progress. It is expected that WSAG will produce an Annual Report to record and disseminate information on progress made and the AWP itself will be reviewed every 5 years (see Action 19).

Figure 3.9 below shows the levels of treatment required over the period of the plan and gives an indication of the stages to be reached to ensure that the waste diversion objectives of the AWP are met on time. These are consistent with the diagrams and tables shown on previous pages.


Figure 3.9 - Proposed Changes in How Waste is Dealt with Between 1998–2020

Figure 3.9 - Proposed Changes in How Waste is Dealt with Between 1998–2020
 
spacer
spacer
Contents Page Contents Page
Previous Page Previous Page
Next Page Next Page
spacer