|
Ayrshire, Dumfries and Galloway |
|
|
|||||||||
|
|||||||||
|
|
|
3.4 Indicative Performance Targets for BPEO Figures 3.5, 3.6 and 3.7 and Tables 3.3, 3.4 and 3.5 outline the objectives of the BPEO with respect to waste diversion by the target years 2010, 2013 and 2020. The proportion of waste diverted to each treatment method is also outlined, as are the diversion targets for each target year. It is implicit that all Landfill Directive Targets will be met within the overall BPEO Targets set out throughout this section and contributes to the 25% recycling and composting national target by 2006. Note the following tables and diagrams share the same underlying assumption. Specifically they are: Modelled on maximum 2% growth rate 'worst case scenario'–SWMBA (2001) Appendix 2. At 0% plus population change, the tonnages would be almost half. Model adjusted to avoid double counting of treatment outputs, i.e. water vapour losses are attributed to compost outputs as well as refuse-derived fuel. Energy from waste refers to pyrolysis/gasification plant in DGC only. The material going to energy recovery is a refuse-derived fuel. All tonnages are indicative and apply across the WSA. They are intended as a guide rather than rigid targets. Individual local authorities may have a different mix of treatments to achieve the overall diversions and these will be set out in local delivery Implementation Plans. If required, other appropriate waste recovery technologies will be used after 2010 to enable the 2013 and 2020 diversion targets to be successfully met. These technologies include processes such as thermal treatment and other emerging waste treatment technologies. These technologies will be assessed for suitability by the WSAG and decision taken by 2006. It should be noted that should recycling and composting activities surpass the percentage shown, then the need for additional technologies will be decreased accordingly. However, should monitoring of the plan indicate that recycling and composting rates will not be sufficient to meet diversion targets, then other appropriate waste-recovery technologies will have to be used to meet the shortfall. The energy from waste element is based on the 30,000 tonnes of refuse-derived fuel that Dumfries and Galloway will be diverting as specified in the Waste Management/Recycling PFI Project. No additional energy from waste elements have been planned for.
Source: Department of Environment, 1992-1993 Household Waste Analysis Programme If we examine the performance of the BPEO against the permitted BMW landfill targets, we can see why the waste strategy group is so confident. Table 3.6 demonstrates that achieving a BMW diversion to satisfy the modelled 'worst-case scenario' is achievable. What is remarkable about this is that no attempt has been made to utilise weight loss from mixed-waste-treatment technologies driving off water vapour and carbon dioxide in the calculations. All the local authorities are looking to introduce some form of additional treatment technology. Dependant on the technology adopted, then between a quarter and half of the weight of waste processed can be diverted as water vapour and CO2, plus they will boost their recycling/composting outputs, plus they can produce an end product suitable for some other use, i.e. not landfilled. Given that the BPEO seeks additional treatment for approximately half of the waste, then a comfortable margin for error can be counted on. Such an approach also allows the treatment of all the putrescibles plus the 'contaminated' fractions that can't be directly recycled/composted.
Source of waste data: SWMBA appendix 2. The amount of BMW going to Landfill is shown in Table 3.7. These figures can then be compared to the maximum amount of BMW allowed to landfill under the directive, as set out in Table 3.8.
Source: Data from SWMBA 2001 Appendix 2 (rounded to nearest thousand) The bottom line is that the BPEO is based on a worst-case scenario. It confidently predicts the delivery of the diversion targets (see Table 3.7 above) with a comfortable factor of safety.
Source: SWMBA 2001 Appendix 2 (rounded to nearest thousand). Proof of the effectiveness of the BPEO will lie in what it delivers. While the WSAG is reluctant to impose fixed targets without a national framework to follow, it has acknowledged that monitoring and review is required, giving an indication of progress. This principle of monitoring and continuous improvement is central to good management. To ensure that the BPEO objectives will be achieved, the WSAG will need to periodically review progress. It is expected that WSAG will produce an Annual Report to record and disseminate information on progress made and the AWP itself will be reviewed every 5 years (see Action 19). Figure 3.9 below shows the levels of treatment required over the period of the plan and gives an indication of the stages to be reached to ensure that the waste diversion objectives of the AWP are met on time. These are consistent with the diagrams and tables shown on previous pages.
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|||||||||
|
|||||||||
|
|