Action |
Obj. |
Target |
Indicator |
Dead-line |
Lead Org |
Resources |
| 1 |
Develop an Area Waste Plan for Western
Isles that fully integrates all waste streams |
2 |
Production of fully integrated Western
Isles Area Waste Plan. |
- Non-MSW BPEO appraisals completed.
- Revised Western Isles Area Waste Plan produced. |
End 2004 |
SEPA |
Existing resources.
Research funds could be needed.
|
| 2 |
Develop a detailed Western Isles Waste
prevention Plan, informed by SEPA's national framework. |
2 |
Production of detailed Western Isles Waste
prevention Plan. |
- SEPA national guidance produced.
- Western Isles local plan completed.
|
End 2004 |
SEPA/ CnES |
Existing resources.
Additional human resources required to develop Plan
(see Action 3). |
| 3 |
Develop and seek funding for additional
posts with specific remits to develop, support and promote waste
prevention initiatives amongst communities and businesses throughout
the islands. |
2,
5,
6,
8 |
Establishment of dedicated local Waste
Prevention and Recycling team. |
- Identification of roles & responsibilities.
- No. of funded posts.
|
End 2003 |
Waste Strategy Area Group |
Specific additional funding required
(possibly local support - e.g. in kind).
|
| 4 |
Waste Strategy Area Group members to
initiate/develop internal programmes to prevent and minimise waste
within their respective organisations. |
2,
8
|
Waste Strategy Area Group members to implement
on-going internal waste prevention programmes |
- No. of Waste Strategy Area Group members with internal
Action Plans (documented).
- Recorded evidence of internal improvements.
|
End 2004 /
ongoing |
Waste Strategy Area Group |
Existing resources |
| 5 |
Promote home composting in very remote
areas of the Western Isles and investigate opportunities for local
discount schemes. |
2 |
Increase in home composting in very remote
rural areas. |
- No. of home composters distributed. |
End 2005 |
CnES |
Existing resources. Additional human
resources may be required (see Action 3) Possible funding required
if subsidised. Can generate savings in waste disposal costs |
| 6 |
Investigate potential for reducing/ recovering
imported packaging waste through partnerships with major retail
organisations. |
2,
8 |
Identification of mechanisms to reduce
imported packaging and increase recovery of imported packaging |
No. of approaches/ meetings with retailers (outcomes)
|
End 2003
|
CnES |
Existing resources Could generate savings
in cost of exporting recyclables (e.g. plastics)
|
| 7 |
Promote greater participation in existing
reuse and refurbishment schemes and develop new and innovative initiatives,
particularly those with local socio-economic benefit. |
2,
5,
8 |
Increase in tonnage of MSW refurbished/
reused |
- No. of local reuse projects.
- Tonnes pa of MSW refurbished/ reused.
|
End 2005 |
CnES |
Existing resources.
Requires additional human resource (see Action 3).
May be potential to part-resource through existing community initiatives
(e.g. voluntary organisations. |
| 8 |
Expand the provision of local recycling
facilities for glass, plastic and metals to ensure easy access for
all Western Isles residents. |
2,
5,
8 |
Target density of 1 recycling site per
250 households outside Stornoway area |
- Density of recycling centres.
- Ave. distance to local recycling centre.
|
End 2005 |
CnES |
Requires specific additional funding. |
| 9 |
Develop and implement a commercial recycling
collection system. |
2,
5,
8 |
Target coverage - tbc |
- No. of commercial participants.
- Tonnes pa of MSW recycled.
|
End 2005 |
CnES |
Requires specific additional funding
Could offer savings to participants. |
| 10 |
Carry out research, including pilot projects,
to assess local suitability of alternative source-segregated BMW
collection systems. |
2,
9 |
Identification of most effective segregated
kerbside collection system for BMW |
- Trial results (yield/capture rates) |
March 2004 |
CnES
|
Existing resources.
Requires specific additional funding (e.g. for trials). |
| 11 |
Carry out research to assess the local
suitability of alternative in-vessel anaerobic digestion and composting
systems. |
2,
5,
9 |
Identification of most appropriate anaerobic
digestion/ composting systems. |
- Report on technical options
- Trial results
|
March 2004 |
CnES/ SEPA |
Existing resources.
Requires specific additional funding (e.g. trials, study visits). |
| 12 |
Develop and implement site conditioning
plans for existing landfill sites to comply with the EU Landfill
Directive. |
1 |
Compliance with EU Landfill Directive. |
- Production of Site Conditioning Plan/s.
- SEPA approval of Site Conditioning Plan/s.
|
March 2003 |
CnES/ SEPA |
Existing resources.
Requires specific additional funding. |
| 13 |
Develop sufficient new transfer capacity
in the Uists and Barra to facilitate disposal of residual MSW at
Bennadrove, and ensure integration of this new capacity with other
strategic waste management requirements. |
2 |
Establishment of sufficient transfer capacity
in the Uists and Barra. |
- Site/s identified.
- Planning permissions granted.
|
End 2006 |
CnES/ SEPA |
Existing resources.
Requires specific additional funding (e.g. site preparation, etc.).
|
| 14 |
Investigate alternative methods for the
collection of household hazardous waste. |
2,
9 |
Identification and cost-benefit assessment
of collection options for HHHW. |
- Research outputs/reports
|
End 2004 |
CnES/ SEPA |
Existing resources. |
| 15 |
Develop and consult on a detailed Area
Waste Plan Implementation Plan to deliver the Western Isles BPEO. |
2,
5,
8,
9 |
Delivery of Western Isles BPEO for MSW. |
- Waste Strategy Area Group Minutes.
- Report on options.
- Production of Implementation Plan.
|
March 2003 |
CnES |
Existing resources (consultancy report
required). |
| 16 |
Identify and where possible quantify
new local markets for reprocessed glass and paper. |
|
Provide sufficient local market capacity
for collected recyclables. |
- Markets identified /quantified
- Trial results
- Demand for products |
End 2004 |
WSAG |
Existing resources. Specific additional
funding may be required for local market surveys. |
| 17 |
In partnership with SWAG, develop a detailed
education and awareness campaign to accompany the introduction of
new collection systems and waste management infrastructure. |
2,
8, |
Production of detailed campaign strategy/
plan |
- SWAG baseline survey Production of fully costed
campaign strategy
|
March 2004 |
CnES/
SWAG |
Existing resources.
SWAG future funding unknown Specific additional funding and human
resources required to implement (e.g. purchase of materials, promotion,
etc). |
| 18 |
Promote and raise awareness of the Western
Isles Area Waste Plan throughout all sectors of the community. |
7,
8 |
Local recognition of Area Waste Plan and
its objectives. |
- No. of specific local presentations.
- Press coverage (column inches).
- Future SWAG survey results.
|
March 2003 |
CnES/ SEPA |
Existing resources. |
| 19 |
Develop and support community-led recycling
initiatives in partnership with the RAGS Community Recycling Network
(CRN) |
2,
8 |
High level of participation in community-led
recycling initiatives. |
- No. of community-led recycling projects
- Tonnes pa of MSW recycled through community-led projects
- Membership of RAGS CRN
|
End 2005/ ongoing |
CnES/ RAGS/ SEPA |
Existing resources.
Additional human resources required to develop/support projects
(see Action 3).
Limited additional funding could be provided through recycling/Landfill
Tax Credits. |
| 20 |
Develop and promote the use of financial
incentive schemes to encourage community-led recycling activity.
|
2,
8 |
Provision of and participation in financial
incentive schemes for community recycling. |
- Identification of options CNES approval.
- No. of community projects supported.
- Level of financial incentive provided. |
End 2004/ ongoing |
CnES |
Some financial provision may be possible
within existing resources (e.g. recycling /Landfill Tax Credits).
However, additional human resources required to develop (see Action
3). |
| 21 |
Collate local non-MSW data and determine
quantities and composition of non-MSW streams for which gaps exist.
|
2,
5,
8 |
Complete baseline non-MSW data set. |
- Production of baseline no-MSW report.
|
End 2004 |
SEPA |
Existing resources. |
| 22 |
Apply national guidance on BPEO assessment
for non-MSW, with priority on fish wastes and agricultural waste. |
2,
5 |
Identification of BPEO for non-MSW |
- Production of national framework for non-MSW Production
of non-MSW baseline report.
- Local option appraisals complete. |
End 2004 |
Waste Strategy Area Group |
Existing resources.
Additional funding may be required for investigation of technical
options, consultations, etc.
|
| 23 |
Investigate potential for a Western Isles
Business Waste Minimisation initiative. |
2,
5,
8 |
Establishment of a Western Isles Business
Waste Minimisation Initiative |
- No. of local companies approached.
- No. of local companies recruited
|
March 2003
|
WIE/ WICC/ SEPA |
Existing resources. Specific additional
funding may be required (but could be provided through Business
WINS, existing LEC funds, etc). |
| 24 |
Relevant lead organisations to report
annually on progress to WSAC against individual action points. |
2,
8 |
Comprehensive Annual Progress Report. |
- Completed individual reports. |
Annual |
Waste Strategy Area Group |
Existing resources. |
| 25 |
WSAC to provide a written annual summary
report on progress against the Action Plan. |
2 |
Effective Area Waste Plan monitoring and
review. |
- Completed Annual Progress Report.
|
Annual |
SEPA |
Existing resources. |
| 26 |
Develop a set of detailed key performance
indicators (KPIs) clearly linked to Area Waste Plan delivery, as
part of CnES Implementation Plan. |
2 |
Effective Area Waste Plan implementation. |
- Identification of KPIs Production of CnES Implementation
Plan
|
March 2003 |
CnES |
Existing resources.
May require consultancy support. |
| 27 |
Objectives, targets and facilities required
to implement the Area Waste Plan taken fully into account in the
development of Structure Plan policy. |
4 |
Effective delivery of BPEO. |
- Site identification.
- Explicit reference to Area Waste Plan objectives.
|
End 2003 |
CnES |
Existing resources. |
| 28 |
Development Plans will ensure suitable
sites are identified to provide the facilities required to deliver
the Western Isles BPEO. |
2,
4 |
Effective delivery of BPEO. |
- Site identification (if appropriate). |
Ongoing |
CnES |
Existing resources. |